Q. What are the timescales for determining each application?

A. The timescales for determination depend on the application type.

Typical timescales are: -

Non-material amendment application


4 weeks.

Prior notifications for agricultural and forestry

4 weeks

Prior approvals larger home extensions

6 weeks

Majority of all other applications and notifications

8 weeks

Applications falling into the category of major

13 weeks

All applications subject to Environmental Impact Assessment (EIA)

16 weeks