Typical timescales are: -
Non-material amendment application
4 weeks.
Prior notifications for agricultural and forestry
4 weeks
Prior approvals larger home extensions
6 weeks
Majority of all other applications and notifications
8 weeks
Applications falling into the category of major
13 weeks
All applications subject to Environmental Impact Assessment (EIA)
16 weeks